JDC installed a complete dewatering system for vertical shaft construction. Installation of 8 deep pumping wells, including electrical and discharge piping. JDC trained general contractor to operate and maintain system throughout construction of shaft.
Additionally, the overall project included the installation of 138,000 lineal feet of horizontal drains from within the vertical shaft, for mass dewatering of the landslide.