North Dakota DOT Tie Back Anchors
Belfield, North Dakota \u2014 Interstate 94
Project Overview
Near Theodore Roosevelt National Park on Interstate 94, an active landslide was causing costly annual paving repairs and ongoing safety concerns for the North Dakota Department of Transportation. JDC was engaged to design and install a permanent solution.
JDC installed 81 multi-strand tie back tendons averaging 140 feet in length as part of a grade beam retention wall system. The project was a pilot design for the DOT to demonstrate the effectiveness of post tensioning as a long-term alternative to repeated surface repairs.
One of the defining challenges was the low-strength formation encountered at the site \u2014 standard anchor grouting alone could not develop adequate bond strength. JDC employed extensive post grouting techniques to build the necessary resistance, successfully achieving design loads in difficult ground conditions.
Comprehensive instrumentation \u2014 including dyna force sensors and load cells \u2014 was installed to monitor anchor performance and validate the design over time. As JDC estimator Casey Cooper noted: "Post grouting was the link to success."
At a Glance
- LocationBelfield, ND (Interstate 94)
- Anchors Installed81 multi-strand tie back tendons
- Average Anchor Length140 feet
- System TypeGrade beam retention wall with post tensioning
- MonitoringDyna force sensors and load cells
- Key TechniqueExtensive post grouting for bond strength
- OwnerNorth Dakota Department of Transportation
- ServiceDOT Landslide Mitigation